Most security doors typically take several weeks from your first enquiry to a fitted, working lock. Manufacturing is usually the stage that decides your total wait, especially if you choose a powder-coated finish, which typically adds a week or more to the schedule. The fastest way to shrink that window is simple: book your on-site measure early and have your colour and hardware choices settled before the technician arrives.
TL;DR:
- Peak season and supply chain issues can extend lead times by a few weeks, especially for custom finishes or imported components.
- Taking rough measurements and choosing finishes before the technician arrives can significantly reduce the waiting period.
- Powder-coating adds roughly one to two extra weeks to production, making early approval of shop drawings crucial for schedule control.
- Proper installation into a solid wall is essential for security, highlighting the importance of professional fitting over DIY methods.
- Homeowners should seek a firm dispatch date and confirm if the supplier offers guaranteed timelines to avoid unnecessary delays.
Table of Contents
- Enquiry, quote and on-site measure: getting a firm number
- Manufacturing lead times: standard builds versus custom finishes
- Installation day: what actually happens and how long it takes
- What actually blows out a lead time
- Cutting your wait: what to do before you even book the measure
- How Eastern Security Doors keeps handoffs to a minimum
- Our take: the timeline homeowners actually need
- Ready to lock in a measure and quote?
- Sources
- FAQ
Enquiry, quote and on-site measure: getting a firm number
Every security door project starts the same way: someone comes to your home, measures the opening properly, and turns that into a quote you can actually rely on. During normal periods, expect to wait one to two weeks for that visit. Push into spring or the run up to Christmas, and it can stretch to three or four weeks as installers work through a longer job list.
The measure itself takes longer than most homeowners expect, and for good reason. A technician checking a single opening will typically:
- Take width and height measurements at multiple points, not just one, because door frames are rarely perfectly square
- Inspect the frame for rot, warping, or previous repairs that could affect fixing points
- Confirm the lock position and check it against your existing door hardware
- Note any access issues, like tight hallways or steps, that could affect the install day
That level of detail matters. A rushed or inaccurate measure is the single biggest reason installation day runs into problems later, from doors that do not sit flush to locks that need re-aligning on the spot. Once the measure is done, most suppliers turn the numbers into a firm quote within a few business days, and your order is locked in once you approve the drawings and pay a deposit.
Manufacturing lead times: standard builds versus custom finishes
Once your deposit clears, the clock starts on the factory build. Standard in-house orders in mild steel or aluminium commonly ship within 7 to 15 working days, a window several Australian manufacturers use as their baseline for straightforward jobs. That figure lines up with supplier-published dispatch targets elsewhere in the industry, which often aim for 7 to 10 working days on unpainted orders.

Powder-coating changes the maths. Because it is usually handled off-site in batches rather than one door at a time, it is a scheduling bottleneck that manufacturers cannot easily compress without charging extra for express finishing. Add roughly one to two weeks to your factory window if you want a colour finish rather than a mill or anodised look.
A few things that stretch or shrink the factory window:
- Standard hinged doors in stock colours: fastest end of the range
- Custom colours or decorative pattern grilles: add time for shop-drawing sign-off and matching
- Doors manufactured and assembled locally often report 2 to 4 week total timelines, noticeably shorter than imported product lines
Pro Tip: Approve your shop drawings the day they land in your inbox. A drawing sitting unread in your email for a week is one of the most common, and most avoidable, causes of a blown schedule.
If you are weighing up finishes for the long term, it is worth reading how powder coat compares with anodised aluminium before you lock in a colour, since switching later means starting the batching queue again.
Installation day: what actually happens and how long it takes
A standard hinged security door usually takes 60 to 90 minutes to fit properly. Sliding doors are often quicker, since there is no swing clearance to set. Double doors, or any job needing frame repair, will run longer.
On the day, a competent installer works through the same sequence regardless of door type:
- Removes the old door or screen and checks the opening is still true to the original measure
- Positions the new door and confirms it sits flush and square in the frame
- Fixes the frame using the correct anchors for your wall type, not a generic screw-and-plug approach
- Fits and tests the lock, adjusting strike plates as needed
- Checks the swing or slide action and hands over keys and warranty paperwork
Fixings matter more than most homeowners realise. A door built to AS5039 standard can still fail as a security barrier if it is anchored into plasterboard instead of a stud or masonry, which is one of the clearest arguments for professional installation over a DIY job.
What actually blows out a lead time
Most delays trace back to one of four things, and knowing which one is at play helps you push back on a vague timeline. Peak season is the most common. Suppliers routinely warn customers directly that spring and pre-Christmas periods push measure bookings, factory queues, and dispatch dates all a little later.
Supply chain conditions are the second factor, and they are largely out of your installer’s hands. Market analysis of the sector shows the industry leans on a mix of local manufacturing and imported steel components, which makes lead times sensitive to shipping schedules and raw-material pricing.
Site conditions are the factor homeowners can actually influence. An out-of-square frame or a doorway needing minor carpentry before the new door goes in will add a return visit if it is not flagged at the measure stage. And the finishing bottleneck already mentioned, powder-coat batching, sits outside your control but is worth asking about upfront:
- Peak season (spring, pre-Christmas): longer waits at every stage
- Supply chain and freight conditions: affect imported components more than local builds
- Site issues found late: frame repairs or packers needed on install day
- Powder-coat batch scheduling: a fixed queue, not a per-order process
Cutting your wait: what to do before you even book the measure
You can shave real time off your schedule with a handful of decisions made before the technician’s van pulls up.
- Take rough measurements and photos of the opening yourself first, so the quote conversation starts with real numbers
- Pick your finish and hardware (locks, mesh type, colour) before the appointment, not during it
- Ask directly about powder-coat batching and whether a guaranteed dispatch date is on offer
- Confirm your installation window at the same time you approve the order and pay the deposit
Pro Tip: Ask your supplier for a written dispatch date, not just a range. “7 to 15 working days” with no start point is not a commitment. A supplier who gives you an actual calendar date has planned your job into their production run.
Homeowners weighing up cost alongside timing might find it useful to check a current security door pricing guide before committing to a finish, since colour and hardware choices affect both budget and schedule together.
How Eastern Security Doors keeps handoffs to a minimum
Fragmented supply chains, where the measure, manufacture, and installation each sit with different businesses, create handoff delays that show up as unexplained gaps in your timeline. Some companies handle measure, manufacture, and installation as one process, which removes several of those handoff points before they can cause a delay.

That structure supports a fast turnaround, along with clear guidance on AS5039 and AS5041 compliance during the quoting stage and installation backed by a warranty. None of that replaces a written dispatch date, but it does mean fewer parties need to coordinate before your door goes in.
Our take: the timeline homeowners actually need
The conventional advice on security door lead times treats every stage as fixed, as though a factory quoting “7 to 15 working days” has told you everything. It has not. That figure describes production capacity, not your actual calendar. The real variable is how fast you move on the decisions within your control: booking the measure, approving the drawing, confirming the finish.
Most homeowners lose more time to indecision on colour and hardware than manufacturers lose to genuine production bottlenecks. Powder-coating is the one exception worth respecting, because that queue genuinely cannot be rushed without paying for it. Everything else on the list, from measure bookings to shop-drawing approval, moves at the pace you set.
If there is one thing worth prioritising above all else, it is asking for a written dispatch date rather than accepting a range. A range protects the supplier’s schedule. A date protects yours.
— MYBMC
Ready to lock in a measure and quote?
Some companies run the measure, manufacture, and installation as one connected process, which can result in a faster turnaround compared to suppliers who outsource one or more of those stages. That means one point of contact, one confirmed install window, and no waiting on a third party’s schedule to line up with your own.

On-site consultations typically cover detailed checks such as multiple measurement points, frame condition, and lock position to help ensure the quote is accurate for manufacturing. Doors are generally built to Australian Standards and may be backed by a warranty on workmanship. Whether you are after an aluminium security door for a coastal property or a stainless steel option for a period home, book your free measure and quote today and get a real dispatch date, not just a range.
Sources
For deeper detail on standard dispatch windows, see the manufacturer FAQ on lead times. The step-by-step installation walkthrough covers what happens on the day in full, and WA Police’s licensing pages outline the regulatory context behind compliant security installations.
- FAQs | Sabretooth
- What happens during a security door installation? A step-by-step walkthrough – OnGuard Security Products
- Security Doors Melbourne | Steel & Aluminium | Custom Made | Smart Doors & Windows
- Steel security doors australia — market analysis and trends
FAQ
What is the Australian standard for security doors?
Security doors and screens sold in Australia are typically built to AS5039 for grille and mesh security doors and AS5041 for hinged and sliding security screen doors, covering strength, mesh gauge, and lock requirements. Suppliers should confirm compliance during your quoting stage, not after the order is placed.
How much does a Crimsafe door typically cost in Melbourne?
Pricing for branded mesh security doors varies by size, finish, and lock hardware, so there is no single figure that applies to every home. A current Melbourne pricing guide breaks down the main cost factors so you can budget before booking a measure.
Do hardware stores offer Crimsafe screen doors?
Big-box hardware retailers generally sell security screen products through in-store consultation rather than direct custom manufacturing, and options are limited to catalogue sizes and finishes. A custom-made door from a specialist supplier gives you exact sizing and finish choices that a standard retail catalogue may not stock.
How long does the whole process take, from enquiry to a fitted door?
Most projects run three to eight weeks in total, covering the measure, manufacturing, and installation stages. Powder-coated finishes and peak-season bookings sit at the longer end of that range, while standard finishes booked outside spring and pre-Christmas periods often land closer to the shorter end, as reported by several Australian manufacturers.
How long does the installation itself take on the day?
A standard hinged security door usually takes 60 to 90 minutes to fit, with sliding doors often quicker and double doors taking longer. Frame repairs found on the day can extend that visit or require a short follow-up appointment.